Martin's Floor
Project Type:
Design/Build
Project Summary:
Reconstruct a previously damaged office/showroom
Project Manager/Engineer:
Frank A. DeMarinis, P.E.
Lead Designer:
Chris Shea
Construction Supervisor:
Mike Clendenin, L.C.S.
Project Description:
Given the task of reconstructing a previously damaged office and showroom, we have designed, permitted, and are now constructing this 10,175 s.f. office/showroom. It is to be a pre-engineered metal building with typical site improvements such as a new driveway, a storm water management system, and typical utilities.
Client:
Martin Malinowski
Location:
Westfield, MA
Design and Permitting:
February to November 2011
Construction Date:
November 2011 to May 2012